OEE (Overall Equipment Effectiveness) is a synthetic indicator of the total effectiveness of manufacturing equipment, widely used in Industry 4.0, TPM (Total Productive Maintenance), and Lean Manufacturing. It is expressed as a percentage and is the product of three component metrics:
OEE = Availability × Performance × Quality
- Availability = actual operating time / planned operating time — measures downtime (breakdowns, changeovers, waiting for material)
- Performance = actual number of pieces / theoretical number at nominal speed — measures slowdowns
- Quality = good pieces / total pieces produced — measures rejects
Practical example: a machine produced 7,500 good pieces in an 8-hour shift at a nominal speed of 1,500 pcs/h. Actual running time 6 hours, 400 reject pieces. Availability = 6/8 = 75%. Performance = (7,900 pieces / (6 h × 1,500)) = 87.8%. Quality = 7,500 / 7,900 = 94.9%. OEE = 75 × 87.8 × 94.9% = 62.5%.
Benchmarks according to TPM methodology:
- 40–60% — typical manufacturing without a TPM programme
- 60–80% — well-managed production
- 85%+ — world-class level
When it is used
OEE is the daily tool of the production manager for identifying bottlenecks — whether the problem lies in maintenance (availability), process settings (performance), or material quality (quality).
See the Production module, the Maintenance module, and the manufacturing industry page.
Related terms
- MES — collects data for real-time OEE calculation. See /en/glossary/mes.
- CMMS — affects the availability component through maintenance. See /en/glossary/cmms.
- MRP — planning that takes into account actual equipment performance via OEE. See /en/glossary/mrp.
In Modulario
The Production module in Modulario automatically calculates OEE from data collected via the MES operator interface. The dashboard displays the OEE trend and its breakdown into three components for each machine, line, and the entire shop floor.
In addition to overall OEE, Modulario breaks performance down into the Six Big Losses: breakdowns, changeovers, minor stoppages, speed losses, start-up rejects, and production rejects. The dashboard shows a Pareto chart of these losses — the manager immediately sees where the greatest improvement potential lies.
Related terms
MES
A system for real-time management and monitoring of production at shop floor level — who, what, on which machine and with what result is happening right now.
CMMS
Software for planning preventive and reactive maintenance of machines, equipment and buildings — service tickets, schedules, spare parts, fault history.
BOM
A structured list of all materials, parts and sub-assemblies required to manufacture one finished product — the foundation for MRP and cost calculations.
MRP
Material requirements planning — calculating what to order or manufacture, when and in what quantity to cover planned orders.
ERP
A comprehensive information system for managing company resources — finance, inventory, production, people and sales in one integrated platform.
Related Modulario modules
Implementing OEE in your company?
Modulario covers most B2B processes modularly — deploy only what you need now and grow gradually. Book a free consultation.
Book a consultation